Overall Timeline
Project Links
Section Design https://www.dropbox.com/s/eqegvwg98ro6c2a/T1D%20All%20Sections.pdf?dl=0
Desktop prototype https://marvelapp.com/1136g8c4/screen/67596000
Mobile prototype https://marvelapp.com/60g257j/screen/67595293
This week’s accomplishments
DEV: Completed final review, updated UX details to complete
DEV: Completed Notifications
PROJECT: Working through UX and development scope and schedule for v1.1 release: managing user accounts and login between the T1D site and TR.
Next week’s plans and goals
DEV: Respond to feedback from Ray on the WP templates
PROJECT: Confirm the steps to update the DNS in advance of the Go Live push
PROJECT: Confirmed that WP will Go Live coincident with the completion of the TR UI updates: August 25
Action items and dependencies
Need to discuss and confirm WP hosting plan (with Newfire?)
Content Strategy
Original content from T1D staff and partners
Aggregated content approved and posted daily via the WP admin dashboard
Editorial rubric to define posting requirements (and limits)
Communication methods
Slack: Project Channel
Hangout: Weekly Syncs, impromptu 1:1s
Zoom: Weekly Review with Rebecca, Charlie and Campbell
Trello: Action Items, Feature Backlog, User Stories
Meetings
Weekly Sync: Mondays at 1pm
Weekly Review: Fridays at 11am
Project risks, consequences and fixes
New pages and copy added to plan.
Donate
For Researchers landing page
Both pages, copy and design, are on track
WP page creation schedule is too aggressive to meet August 3rd goal.
Page creation and approvals may take more than three weeks
Mid to late August is more likely
Confirmed August 25 Go Live date
WP to TR funnel scheduled for v1.1 release
UX and Development scoping currently underway
TR and WP changes 95% confirmed. Need discussion/decision to implement