Overall Timeline

T1D Site Update August 5, 2020.png
 

This week’s accomplishments

  • DEV: Completed final review, updated UX details to complete

  • DEV: Completed Notifications

  • PROJECT: Working through UX and development scope and schedule for v1.1 release: managing user accounts and login between the T1D site and TR.

 

Next week’s plans and goals

  • DEV: Respond to feedback from Ray on the WP templates

  • PROJECT: Confirm the steps to update the DNS in advance of the Go Live push

  • PROJECT: Confirmed that WP will Go Live coincident with the completion of the TR UI updates: August 25

 
Artboard.png
 

Action items and dependencies

  • Need to discuss and confirm WP hosting plan (with Newfire?)

Content Strategy

  • Original content from T1D staff and partners

  • Aggregated content approved and posted daily via the WP admin dashboard

  • Editorial rubric to define posting requirements (and limits)

Communication methods

  • Slack: Project Channel

  • Hangout: Weekly Syncs, impromptu 1:1s

  • Zoom: Weekly Review with Rebecca, Charlie and Campbell

  • Trello: Action Items, Feature Backlog, User Stories

Meetings

  • Weekly Sync: Mondays at 1pm

  • Weekly Review: Fridays at 11am

Artboard_1.png

Project risks, consequences and fixes

  • New pages and copy added to plan.

    • Donate

    • For Researchers landing page

    • Both pages, copy and design, are on track

  • WP page creation schedule is too aggressive to meet August 3rd goal.

    • Page creation and approvals may take more than three weeks

    • Mid to late August is more likely

    • Confirmed August 25 Go Live date

  • WP to TR funnel scheduled for v1.1 release

    • UX and Development scoping currently underway

    • TR and WP changes 95% confirmed. Need discussion/decision to implement